Hello,
I am using plantuml 1.2018.08
With the following plantuml script
@startuml
[SA] lasts 2 days[LLA1] lasts 8 days
[BS] lasts 3 days
[LLA1] -> [BS]
[SA] -> [LLA1]
@enduml
Task BS is not correctly scheduled. I would expect it to start on the 11th day, after [LLA1] has ended. Instead, the dependency goes backwards in time and starts on the 9th day.
Can someone explain this behavior ? This seems counter intuitive. How can I configure it ?
Kind regards,