Hi,is there a possibility to start a task in a gantt diagram two days after an other task has been started.
Something like
[s2] starts at [s1]'s start + 2
Regards
Jens
(--------)
Hi J., and all,
For that you can use:
[s2] starts 2 days after [s1]'s start
As:
@startgantt [s1] lasts 4 days [s2] lasts 5 days [s2] starts 2 days after [s1]'s start @endgantt
Enjoy,Regards.