gantt diagram: how can I start a task after a milestone

0 votes
asked Sep 29, 2020 in Question / help by PascalChap (340 points)

When I use acmilestone to identify the maximum end of several tasks, I would like to be able to use this miles stone as a reference to start a new task. I have tried several syntax, but always got a syntax error message. How to achieve this?

https://www.plantuml.com/plantuml/png/SoWkIImgIK_CAodXuYeeoizAJIvH08iLAnWP61dg6fZh6XXoSKMxbgNcbSGgP2GM5AJc8ScP0kL24ekpOnNoavDBYueLqehoSnLWoXFpKXHo4el1XYca95OMSt4vfEQbWEq30000

1 Answer

0 votes
answered Sep 29, 2020 by The-Lu (64,340 points)
selected Sep 29, 2020 by PascalChap
 
Best answer

Hello P.,

The current syntax is:

project starts 2021-07-01
[Event] happens 2021-07-05
[Task] starts at [Event]'s end and lasts 20 days


[See on PlantUML server]

See also on:

If that can help,
Regards,
Th.

commented Sep 29, 2020 by PascalChap (340 points)

yes Thank you.I didn't try this combination.

...