How about add a vertical line to indicate current date of Gantt

0 votes
asked Sep 17, 2025 in Wanted features by JohnKnow (120 points)
As the subject.

1 Answer

0 votes
answered Sep 17, 2025 by Serge Wenger Work (16,630 points)
selected Sep 22, 2025 by JohnKnow
 
Best answer

@startgantt
Project starts 2025-09-15
today is colored in Blue
[Prototype design] requires 15 days
[Test prototype] requires 10 days
@endgantt

...