Odd computation of date in Gantt

0 votes
asked 2 hours ago in Bug by Florimond (120 points)
Why the date of the red activity is calculated like that ?

@startgantt

  Project starts 2026-08-20

  [K1 C S I_A24] happens 2026-08-26
  [K1 C S A24] requires 4 weeks
  [K1 P_A24] requires 15 days

  [K1 C S A24] starts at [K1 C S I_A24]'s end
  [K1 P_A24] starts at [K1 C S A24]'s end

  [K2 T_A24] requires 15 days
  [K2 P_A24] requires 15 days

  [K2 P_A24] starts at [K2 T_A24]'s end
  
  [K2 P_A24] is colored in red

  [K2 T_A24] starts at [K1 P_A24]'s end

  [Setup] starts 2026-11-10
  [Setup] ends 2026-12-07

  [test_A12] requires 2 weeks
  [test_A12] starts at [Setup]'s end
  [test_A12] starts at [K2 P_A24]'s end

@endgantt

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:

[Antispam2 Feature: please please wait 1 or 2 minutes (this message will disappear) before pressing the button otherwise it will fail](--------)
To avoid this verification in future, please log in or register.
...