closed Odd computation of date in Gantt

0 votes
asked Aug 28 in Bug by Florimond (120 points)
closed 13 hours ago by Florimond
Why the date of the red activity is calculated like that ?

@startgantt

  Project starts 2026-08-20

  [K1 C S I_A24] happens 2026-08-26
  [K1 C S A24] requires 4 weeks
  [K1 P_A24] requires 15 days

  [K1 C S A24] starts at [K1 C S I_A24]'s end
  [K1 P_A24] starts at [K1 C S A24]'s end

  [K2 T_A24] requires 15 days
  [K2 P_A24] requires 15 days

  [K2 P_A24] starts at [K2 T_A24]'s end
  
  [K2 P_A24] is colored in red

  [K2 T_A24] starts at [K1 P_A24]'s end

  [Setup] starts 2026-11-10
  [Setup] ends 2026-12-07

  [test_A12] requires 2 weeks
  [test_A12] starts at [Setup]'s end
  [test_A12] starts at [K2 P_A24]'s end

@endgantt
closed with the note: Provided answer is fine

1 Answer

+1 vote
answered 20 hours ago by The-Lu (90,460 points)
selected 13 hours ago by Florimond
 
Best answer
...