Hello,
In a gantt diagram, if you start a project on a day off, and if the diagram uses a statement such as :
[task] pauses on monday
then the paused days are not at the right place.
example with error:
http://www.plantuml.com/plantuml/png/DSqn3i8m58FXFQVm4K87vXw1WGqnF1931MqUYby7RWzKwlfPrZyghCV3MaGwTN-o13OIOYAECS7lg2nSRkmOyf2JrbRj0-j4cLsiwN8slQwOJI4SCdwpTdpRAWhUiFZ_bqQskWM_
http://www.plantuml.com/plantuml/png/DSqn3i8m58FXFQVm4K8NrXw1WGqnF1931MqUYby7RWzKwlfPrZyghCV3MaGwTN-o13OIOYAECS7lg2nSRkmOyf2JrbRj0-j4cLsiwN8slQwOJI4SCdwpTdpRAWhUiFZ_bqQskWM_
example without error:
http://www.plantuml.com/plantuml/png/DSqn3i8m58FXFQVm4K8bzXw1WGqnF1931MqUYby7RWzKwlfPrZyghCV3MaGwTN-o13OIOYAECS7lg2nSRkmOyf2JrbRj0-j4cLsiwN8slQwOJI4SCdwpTdpRAWhUiFZ_bqQskWM_
(--------)