Disable task scaling when resources are added

0 votes
asked Nov 19 in Wanted features by WD83 (120 points)
I noticed that tasks are scaled when they are resourced:

"[Foo] on {Bob:50%} lasts 10 days" will occupy 20 days, while

"[Foo] on {Bob} {Charlie} lasts 10 days" will occupy 5 days.

Could you add an option to disable this?  I like the resourcing feature to know when I've overburdened someone, but two people will rarely take half the time to execute a task, especially if one of them is inexperienced.  I'd rather trust myself to do the duration estimation.