Hello A.,
See similar request here:
with:
One question: Does this mean that its now week numbers instead of the week starting date?Yes, exactlyI suspect that both options are of interest, to different people / different situations.We'll see if people complains about it, and we will then add an option :-)
One question: Does this mean that its now week numbers instead of the week starting date?
Yes, exactly
I suspect that both options are of interest, to different people / different situations.
We'll see if people complains about it, and we will then add an option :-)
Ref. https://forum.plantuml.net/11630/gantt-weekscale-with-weeknumbers?show=13592#c13592
Regards,Th.
(--------)
You can now use:
printscale weekly with calendar date
With that:
@startuml printscale weekly with calendar date Project starts the 6th of July 2020 [Task1] on {Alice} lasts 2 weeks [Task2] on {Bob:50%} lasts 2 weeks then [Task3] on {Alice:25%} lasts 3 days @enduml
See: