Gantt: Closed days aren't ignored when delaying tasks

0 votes
asked Jun 28 in Bug by anonymous

When delaying tasks in a gantt diagram the expected behavior would be that closed days are ignored. Since all other time values also ignore closed days. Instead you have to count closed days + delayed days.

Example:

@startgantt

saturday are closed
sunday are closed
2022-07-04 to 2022-07-15 is closed

Project starts 2022-06-27
[task1] starts at 2022-06-27 and lasts 1 week
[task2] starts 2 days after [task1]'s end and lasts 3 days

@endgantt

I would expect task2 to last from Wednesday (2022-07-20) to Friday (2022-07-22). Since the begin after the closed days is Monday (2022-07-18) and delayed by two days would be Wednesday. But to achieve this behavior I have to do the following:

@startgantt

saturday are closed
sunday are closed
2022-07-04 to 2022-07-15 is closed

Project starts 2022-06-27
[task1] starts at 2022-06-27 and lasts 1 week
[task2] starts 18 days after [task1]'s end and lasts 3 days

@endgantt

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:

[Antispam2 Feature: please please wait 1 or 2 minutes (this message will disappear) before pressing the button otherwise it will fail](--------)
To avoid this verification in future, please log in or register.
...