Hello E. and all,
That was not yet implemented...
See similar request here:
Then, in continuation of other plantuml functionalities, here is a proposal (for the syntax, using stereotypes) for a wanted feature:
@startgantt
<style>
.BlackArrow {
ganttDiagram {
arrow {
LineColor Black
}
}
}
.GreenArrow {
ganttDiagram {
arrow {
LineColor Green
}
}
}
.Critical {
task {
lineColor red
}
}
</style>
[01] requires 5 days
then [10] requires 2 days
[Block 1] starts at [01]'s start and ends at [10]'s end <<GreenArrow>>
[11] requires 2 days
then [15] requires 3 days
[Block 2] starts at [11]'s start and ends at [15]'s end <<BlackArrow>> <<Critical>>
@endgantt
To debate...
Perhaps other proposal are possible... like `is styled on BlackArrow and Critical`...
Awaiting full style management with stereotype on Gantt chart...
Regards,
Th.