How to get the calculated dates from gantt chart?
0
votes
asked
5 days
ago
in
Question / help
by
jotabanp
(
160
points)
Hello,
When using the gantt chart, I set the project start date and add the tasks and its dependecies, so the plantuml engine calculates the end's date of these tasks.
How can I get or see these end's date tasks?
Thank you.
gantt
date
Your comment on this question:
Your name to display (optional):
Email me at this address if a comment is added after mine:
Email me if a comment is added after mine
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:
To avoid this verification in future, please
log in
or
register
.
Your answer
Your name to display (optional):
Email me at this address if my answer is selected or commented on:
Email me if my answer is selected or commented on
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:
[Antispam2 Feature: please please wait 1 or 2 minutes (this message will disappear) before pressing the button otherwise it will fail]
(--------)
To avoid this verification in future, please
log in
or
register
.
Related questions
Gantt crashes with specific Project start dates
Gantt diagram - how to start a project a number of days before today?
How to start a task in a gantt chart at day 10 (or X) when not using dates
Is it possible to show calculated start and end dates in gantt?
How to change the default color for closed days in Gantt chart?
All categories
Question / help
(1,710)
Bug
(1,760)
Wanted features
(1,480)
Closed question / help
(89)
Closed bug
(53)
Closed feature request
(130)
Won't fix
(3)
Won't implement
(14)
Can't help
(10)
To be deleted
(10)
To be sorted
(431)
...