Allow constraints to be specified after aliasing a Gantt task

0 votes
asked Feb 27, 2018 in Wanted features by Chris
I'd like to be able to specify relationships between tasks after defining them, like so:

@startgantt

[Task 1] as [task1] lasts 1 days

[Task 2] as [task2] lasts 2 days

[Task 3] as [task3] lasts 2 days

task1 -> task2

task3 starts at task2's end

@endgantt

1 Answer

0 votes
answered Feb 28, 2018 by Serge Wenger Work (15,620 points)

Hello,

@startgantt
[Task 1] as [task1] lasts 1 days
[Task 2] as [task2] lasts 2 days
[Task 3] as [task3] lasts 2 days
task1 -> task2
[task3] starts at [task2]'s end
@endgantt

...