[Gantt] Issue with yearly print when project does not begin at beginning of year

0 votes
asked Apr 4, 2021 in Wanted features by The-Lu (63,920 points)

Hello PlantUML team,

Thanks for this enhancement (Add quarterly and yearly print scale to gantt diagram), and for @Loïc Péron,

But, we observe (on 1.2021.4) :

  • Issue with yearly print when project does not begin at beginning of year.

Here are examples:

1/ Project starts at beginning of year: OK

@startgantt
projectscale yearly
Project starts the 2020-01-01
[Prototype design] starts 2020-07-01 and lasts 400 days
@endgantt

2/ Project starts on the middle of year: KO, overlap of year title

@startgantt
projectscale yearly
Project starts the 2020-07-01
[Prototype design] lasts 400 days
@endgantt

Regards,
Th.