Two workers on one task starting at different times

0 votes
asked Oct 15 in Question / help by AKielhorn (180 points)

I have a question similar to

https://forum.plantuml.net/18397/gantt-how-handle-resource-starts-terminates-specific-date

One worker is working on Job-1.

Once he finished that, he will start Job-2.

A second worker will start on Job-2 while worker one is still on Job-1.

@startgantt
project starts the 2025/10/01
saturday are closed
sunday are closed

[Job-1]    as [J1] on {BKI} lasts 13 days
[Job-2]    as [J2] lasts 9 days
[J2] on {BKI} starts after [J1]'s end
[J2] on {AKI} starts at 2025-10-15

@endgantt

I came up with the following, but it requires manual adjustment of the workload.

I'd rather prefer to start Job-2 on 2025-10-15 and add resource BKI once Job-1 is finished.

@startgantt
project starts the 2025/10/01
saturday are closed
sunday are closed

[Job-1]    as [J1] on {BKI} lasts 13 days
[Job-2]    as [J2a] lasts 3 days
[Job-2]    as [J2b] lasts 6 days
[J2a] on {BKI} starts after [J1]'s end
[J2b] on {AKI} starts at 2025-10-15

@endgantt

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:

[Antispam2 Feature: please please wait 1 or 2 minutes (this message will disappear) before pressing the button otherwise it will fail](--------)
To avoid this verification in future, please log in or register.
...