I have a question similar to
https://forum.plantuml.net/18397/gantt-how-handle-resource-starts-terminates-specific-date
One worker is working on Job-1.
Once he finished that, he will start Job-2.
A second worker will start on Job-2 while worker one is still on Job-1.
@startgantt
project starts the 2025/10/01
saturday are closed
sunday are closed
[Job-1] as [J1] on {BKI} lasts 13 days
[Job-2] as [J2] lasts 9 days
[J2] on {BKI} starts after [J1]'s end
[J2] on {AKI} starts at 2025-10-15
@endgantt
I came up with the following, but it requires manual adjustment of the workload.
I'd rather prefer to start Job-2 on 2025-10-15 and add resource BKI once Job-1 is finished.
@startgantt
project starts the 2025/10/01
saturday are closed
sunday are closed
[Job-1] as [J1] on {BKI} lasts 13 days
[Job-2] as [J2a] lasts 3 days
[Job-2] as [J2b] lasts 6 days
[J2a] on {BKI} starts after [J1]'s end
[J2b] on {AKI} starts at 2025-10-15
@endgantt