Could be possible to define simply Task between two Milestones?

0 votes
asked Jul 29, 2020 in Wanted features by The-Lu (63,920 points)

Hello PlantUML team,

Adapted from: https://forum.plantuml.net/11877/how-to-change-color-or-thickness-style-arrows-gantt-diagram

  • Would be possible to define simply Task between two Milestones?
From:
Here is a proposal, to remplace:
[Prototype design] starts at [P_start]'s end and ends at [P_end]'s start
by:
[Prototype design] from [P_start] to [P_end]

  • Answer to us if this proposal is acceptable or not?
Regards,
Th.

1 Answer

+1 vote
answered Jul 29, 2020 by plantuml (294,960 points)
Hi,

Thanks for the suggestion: this is indeed a good idea !

We are going to take some days off, so we will implement this in August...

Please be patient :-)

Regards and thanks again !
commented Jul 31, 2020 by The-Lu (63,920 points)

Hi,

Thank you for this consideration.
Moreover with the already big list of defect reports or wanted features requests.

Have good days off.
Regards,
Th.

commented Aug 24, 2020 by plantuml (294,960 points)

With last official release, you can have :

@startgantt
project starts on 2020-07-01
[P_start] happens 2020-07-03
[P_end]   happens 2020-07-13
[Prototype design] occurs from [P_start] to [P_end]
@endgantt

...