Milestones and tasks do not sequence in an easy manner.
Let start with an example from the documentation :
@startgantt
[Test prototype] requires 10 days
[Prototype completed] happens at [Test prototype]'s end
[Setup assembly line] requires 12 days
[Setup assembly line] starts at [Test prototype]'s end
@endgantt
Now imagine that I have forgot to pop champaign after test prototype. I have to add a new linne for this task, but also to edit the milestone line, as below :
@startgantt
[Test prototype] requires 10 days
then [pop a bottle] requires 1 day
[Prototype completed] happens at [pop a bottle]'s end
[Setup assembly line] requires 12 days
[Setup assembly line] starts at [Test prototype]'s end
@endgantt
I think it would be easier to be able to sequence a milestone using then, making easier this kind of update :
@startgantt
[Test prototype] requires 10 days
then [pop a bottle] requires 1 day
then [Prototype completed] happens
[Setup assembly line] requires 12 days
[Setup assembly line] starts at [Test prototype]'s end
@endgantt
The same can also apply to sequence the first task after a milestone :
@startgantt
[Test prototype] requires 10 days
then [pop a bottle] requires 1 day
then [Prototype completed] happens
then [Clean the mess] requires 1 day
then [Setup assembly line] requires 12 days
@endgantt
Thanks for your attention.
Regards,
PMZ