Could be possible to define simply Task between two Milestones?

0 votes
asked 5 days ago in Wanted features by The-Lu (5,860 points)

Hello PlantUML team,

Adapted from: https://forum.plantuml.net/11877/how-to-change-color-or-thickness-style-arrows-gantt-diagram

  • Would be possible to define simply Task between two Milestones?
From:
Here is a proposal, to remplace:
[Prototype design] starts at [P_start]'s end and ends at [P_end]'s start
by:
[Prototype design] from [P_start] to [P_end]

  • Answer to us if this proposal is acceptable or not?
Regards,
Th.

1 Answer

+1 vote
answered 5 days ago by plantuml (226,800 points)
Hi,

Thanks for the suggestion: this is indeed a good idea !

We are going to take some days off, so we will implement this in August...

Please be patient :-)

Regards and thanks again !
commented 3 days ago by The-Lu (5,860 points)

Hi,

Thank you for this consideration.
Moreover with the already big list of defect reports or wanted features requests.

Have good days off.
Regards,
Th.

...