Gantt diagram: task duration in minutes and hours

0 votes
asked Jun 28, 2022 in Question / help by Lora
How can I set the task duration of the tasks on the daily scale to minutes or hours?
commented Jun 28, 2022 by Lora
Thank you for your quick reply,

None of the solutions discussed in the links above will work for me, as I would need to use minutes, hours and days at the same diagram.
If I equal 1 day to 1 minute the resulting diagram will be humongous (and unreadable). I will also have to find a way to remove the year / month / day heading located at the top of the diagram.

Regarding the question
"If we go under day level, then we have to think about how to define working hours.

I mean, we cannot assume that a day is a 24 hours working day. So we have to define working hours (for example : 8am -> 12pm then 2pm-> 6pm).

Or we have to works with fractionnal load. (A task during 4.75 days for example).

Not sure which solution is the best."

I propose the following:
workweek, (with or without date range): Mon, Tue, Wed, Thu, Fri, Sat, Sun
workweek: all
workweek: Mon - Wed, Fri

If a day is defined as 00:00 to 24:00
working hours, (with or without day or date range): all
working hours: 00:00 - 24:00
working hours: 9:00 - 12:00, 14:00 - 18:00
working hours: 8:00 - 18:00
working hours: 8:00 - 20:00
working hours: 8:05 - 10:15, 14:30 - 17:00, 18:11 - 19:01

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:

[Antispam2 Feature: please please wait 1 or 2 minutes (this message will disappear) before pressing the button otherwise it will fail](--------)
To avoid this verification in future, please log in or register.
...